Thread regarding ExxonMobil Corp. layoffs

Golden Pass

What’s the latest on Golden Pass

by
| 1592 views | | 8 replies (last January 30, 2025) | Reply
Post ID: @OP+1jjewwbww

8 replies (most recent on top)

There was a time where we didn’t bankrupt our contractors. What a joke. We will end up paying more and taking longer. Lose on cost and schedule. And for what? To make a point somehow? So much winning!

by
| | Reply
Post ID: @ye+1jjewwbww

Golden Pass=Little Alberta

by
| | Reply
Post ID: @wz+1jjewwbww

@s5+1jjewwbww

Not according to the press releases from Public and Government Affairs.

by
| | Reply
Post ID: @t1+1jjewwbww

It’s ahead of schedule and under budget

by
| | Reply
Post ID: @s5+1jjewwbww

The DoAGs that are part of this are covered and there is plenty of money. No layoffs. Maybe more contractors not getting paid. This will drag out however long it takes while the rest of us pinch Pennie’s

by
| | Reply
Post ID: @gw+1jjewwbww

Great place for our expats returning from the United States.

Partners ExxonMobil (XOM) and Qatar Energy have pushed back the start date for Golden Pass LNG to late 2025 following the bankruptcy of lead contractor Zachry Holdings, Bloomberg reports. East Daley Analytics assumes a January ’26 start for Train 1 of the Golden Pass project in our latest monthly natural gas forecasts.

Golden Pass LNG will start operations six months later than previously planned as a result of work stoppages from the Zachry bankruptcy, XOM CFO Kathy Mikells told Bloomberg. Zachry filed for Chapter 11 protection in May ’24 seeking an exit as the lead engineering, procurement and construction (EPC) contractor for the project.

The partners and Zachry reached a settlement agreement in July that removes Zachry and allows Chiyoda to take over as the EPC lead for the project under construction near Sabine, TX. As of the latest work stoppage, Train 1 at Golden Pass LNG was 83% complete, according to a progress report filed with the Federal Energy Regulatory Commission (FERC). Train 2 and Train 3 were 46% and 31% complete, respectively. As part of the original EPC joint venture, Chiyoda was only responsible for the commissioning phase of Train 1.

East Daley had already pushed back the expected start date of the Golden Pass facility after the two-month bankruptcy proceeding halted momentum. In the latest monthly Macro Supply & Demand Forecast, we expect Golden Pass Train 1 to begin service in January 2026. EDA’s new regional gas models also reflect the project delay.

Despite the postponement, the demand outlook remains strong for LNG exports in 2025. The figure shows EDA’s LNG project stack in Energy Data Studio. Several other projects plan to start in the next year, including Cheniere Energy’s (LNG) Corpus Christi Phase III and Venture Global’s Plaquemines LNG, and should contribute to growth. – Oren Pilant & Andrew Ware Tickers: LNG, XOM.

https://www.eastdaley.com/media-and-news/golden-pass-lng-start-delayed-to-late-2025

by
| | Reply
Post ID: @bq+1jjewwbww

Probably cause the people would be laid off if they shut it down. @bg+1jjewwbww

by
| | Reply
Post ID: @bm+1jjewwbww

What does that have to do with layoffs?

by
| | Reply
Post ID: @bg+1jjewwbww

Post a reply

: