Thread regarding General Electric Co. layoffs

Liquified Natural Gas Facility Greenville

How much money was wasted building the LNG facility in Greenville that never liquified natural gas? This is the same GE location that builds Gas turbines that are failing. I am guessing GE invested $70 Million on a facility that never functioned per design.

by
| 1832 views | | 8 replies (last October 13, 2018) | Reply
Post ID: @OP+VCZSKBZ

8 replies (most recent on top)

You're not missing anything. They ended up trucking in the LNG, did an investigation and decided not to fix it but instead go with a workaround.

by
| | Reply
Post ID: @vzq+VCZSKBZ

I am missing something about the LNG facility. Are you saying GE invested $70 Million in a facility and after it didn’t work it didn’t matter?

by
| | Reply
Post ID: @rte+VCZSKBZ

WTF does this have to do with Stokes? What's next, you're going to blame him for a parking lot fender bender?

by
| | Reply
Post ID: @vya+VCZSKBZ

How long Stokes will be around? Any one knows?

by
| | Reply
Post ID: @zyc+VCZSKBZ

No. Wrong. It was supposed to take gaseous NG off the pipeline 24hrs a day, store it as LNG then vaporize it as needed. It was cheaper to do that than upgrade the pipeline. It doesn't do that and GE, when it had the money, didn't care to fix it.

by
| | Reply
Post ID: @abu+VCZSKBZ

Uses LNG (take liquid NG and converts to gas), does not make LNG (takes NG and turns to liquid). We consume more than the pipeline will provide for testing.

by
| | Reply
Post ID: @kkw+VCZSKBZ

They use it everyday as part of the test stands.

by
| | Reply
Post ID: @nwz+VCZSKBZ

Hmmm

by
| | Reply
Post ID: @fpx+VCZSKBZ